单项选择题
In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
A. schedule
B. WBS
C. SOW
D. charter
点击查看答案&解析
相关考题
-
单项选择题
( )can be considered as part of risk mitigation.
A. Risk identification
B. Purchasing insurance
C. Assessment of outcomes
D. Assessment of probabilities -
单项选择题
( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
A. Allowing looping
B. Allowing for dummy tasks
C. Allowing branching
D. Allowing multiple project end results -