未知题型
The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……
A.Monitoring
B.Managing
C.Gathering
D.Reducing
- A.(73)all
B.Monitoring
B.Managing
C.Gathering
【参考答案】
B
解析:在项目的生命周期里,项目通过如下措施维持一个最新的、经批准的需求集合:
. 管理对需求的变更。......