项目管理中,保证客户和干系人满意的最重要活动是(34)。
D.将需求记录下来整理为文件
- A.绩效测评存档
B.变更汇报和项目计划更新以及其他适当的项目文件
C.及时且有规律地汇报项目绩效
【参考答案】
D
解析:本题的选项A、B、C对客户和其他项目干系人也很重要,但重要的是获取他们的需求、分析他们的需求、让他们确...
(↓↓↓ 点击下方‘点击查看答案’看完整答案 ↓↓↓)
点击查看答案
相关考题
- 判断题 实现将公共数据上的数字信号按要求分配到不同电路中去的电路叫数据分配器。 正确 错误
- 未知题型 下图中活动G可以拖延(36)周而不会延长项目的最终结束日期。(图中时间单位为周)A.0B.1C.3D.4
- 单项选择题 渣的粘度越大,使用温度越高,耐火材料在渣中的溶解速度越快( )
- 单项选择题 He has never shown any inclination to ____ pressure in any area or from any other person. A、bow B、bow to C、bow over D、bow out
- 问答题 在分析夹紧力时, 可把螺旋看作是一个缠绕在圆柱体上的斜面, 展开后就相当于________________了。
- 未知题型 The project maintains a current and approved set of requirements over the life of the project by doing the following: .(73)all changes to the requirements . Maintaining the relationships among the requirements, the project plans, and the work products . ……A.MonitoringB.ManagingC.GatheringD.Reducing
- 多项选择题 科学精神表现为() A. 怀疑精神 B. 求真精神 C. 创新精神 D. 务实精神
- 单项选择题 Waves that travel very long distances are called ( )
- 未知题型 The word 'diurnal'(Line 3, Para 3) is closest in meaning to______.A.day-and-night'sB.everydayC.two daysD.yearly
- 未知题型 We all know that the normal human daily cycle of activity is of some 748 hours' sleep alternating with some 16,417 hours' wakefulness and that, broadly speaking, the sleep normally coincides with the hours of darkness. Our present concern is with how easily and to what extent this cycle can be modifieD.The question is no mere academic onE.The ease, for example, with which people can change from working in the day to working at night is a question of growing importance in industry where automation calls for round-the-clock working of machines. It normally takes from five days to one week for a person to adapt to a reversed routine of sleep and wakefulness, sleeping during the day and working at night. Unfortunately, it is often the case in industry that shifts are changed every week: a person may work from 12 midnight to 8 A.m. one week, 8 A.m. to 4 p.m. the next, and 4 p. m. to 12 midnight the third and so on. This means that no sooner has he got used to one routine than he has to change to another, so that much of his time is spent neither working nor sleeping very efficiently.The only real solution appears to be to hand over the night shift to a number of permanent night workers. An interesting study of the domestic life and health of night shift workers was carried out by Brown in 1957. She found a high incidence of disturbed sleep find other disorders among those on alternating day and night shifts, but no abnormal occurrence of these phenomena among those on permanent night work.This latter system then appears to be the best long-term policy, but meanwhile something may be done to relieve the strains of alternate day and night work by selecting those people who can adapt most quickly to the Changes of routinE.One way of knowing when a person has adapted is by measuring his body temperaturE.People engaged in normal day-time work will have a high temperature during the hours of wakefulness and a low one at night; when they change to night work the pattern will only adjust gradually back to match the new routine and the speed with which it does so parallels, broadly speaking, the adaptation of the body as a whole, particularly in terms of performancE.Therefore, by taking body temperature at intervals of two hours throughout the period of wakefulness it can be seen how quickly a person can adapt to a reversed routine, and this could be used as a basis for selection. So far; however, such a form. of selection does not seem to have been applied in practicE.Why is the question of 'how easily people can get used to working at flight' no mere academic one?A.Because few people like to reverse the cycle of sleep and wakefulness.B.Because sleep normally coincides with the hours of darkness.C.Because people are required to work at night in some fields of industry.D.Because shift work in industry requires people to change their sleeping habits.